Interactive Map

Get project specific information by clicking its name below or its location on the map.

Under Construction

In Design

Force Main 1

  • Bradenton Beach

The FM 1 project will replace a combination of 4, 6 and 8-inch force main pipeline. Approximately one-half mile of new pipeline will be installed. The project starts on Church Avenue from Cortez Road West to Bridge Street. At Bridge Street the project shifts to Bay Drive South and runs to 5th Street South. The project continues along 5th Street South to Gulf Drive North where it turns and runs south to 6th Street South. It then travels along 6th Street South to the end of the street.

Also included with this project is construction of approximately 800 feet of 10-inch gravity sewer pipe along 5th Street South to Gulf Drive North, Gulf Drive North to 6th Street South, and 6th Street South.

Under Construction

Force Main 8

  • Holmes Beach

The FM 8 project will replace a little over one-quarter mile of 6-inch force main pipeline. This pipeline will be installed on Marina Drive from 72nd Street and 68th Street.

Construction scheduled to begin 2019/2020

Force Main 15

  • Anna Maria

The FM 15 project will replace a little over one-quarter mile of 6-inch pipeline along North Bay Blvd from Hibiscus Road to North Pine Avenue.

Construction scheduled to begin 2019/2020

Coquina Beach Drainage Improvements

  • Coquina Beach

Drainage improvements are underway in the Coquina Beach public parking areas. Currently the southern end of the Coquina Beach parking lot is closed while construction crews work to improve stormwater drainage and parking conditions. This is Phase 1 of a two-phase project to reduce flooding at this popular public beach.

Phase 1 is scheduled to be complete in the spring of 2020. Once Phase 1 is complete, crews will move to the north end of the parking lot and continue the drainage improvements work. However, unlike in Phase 1, large areas of parking will not be impacted by the work at the north end as the work can be done in smaller segments over time.

In addition to improving stormwater drainage, work also involves striping parking spaces. Currently the park has shell parking without any markings. When all of the work is complete there will be 865 parking spaces at Coquina Beach.

Under construction

Holmes Boulevard Force Main Replacement

  • Holmes Beach

The Holmes Blvd. Force Main Replacement project will replace just under one mile of 12 and 10-inch force main pipeline on Holmes Blvd from 68th Street to 52nd Street. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020

 

AMI Watermain Improvements

  • Bradenton Beach

This project will replace and upsize 2-inch and 4-inch water lines along 26th Street North, 25th Street North, and Avenue A. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020