Interactive Map

Get project specific information by clicking its name below or its location on the map.

Under Construction

In Design

Force Main 1

  • Bradenton Beach

As construction work continues along Gulf Drive on Force Main 1 in Bradenton Beach, the safety of residents, visitors, the traveling public and work crews is our primary concern. We urge all commuters to adhere to the posted speed limit of 25 m.p.h. when traveling along Gulf Drive.

The replacement of a 10-inch sanitary sewer line at a depth of 15 feet and a 6-inch force main pipeline along Gulf Drive between 6th Street South and 5th Street South was completed on May 22, 2020. In addition, asphalt replacement along Gulf Drive travel lanes and on bike paths between 6th Street South and 5th Street South was also completed. Currently crews are working on clean-up and restoration on Gulf Drive. All travel lanes on Gulf Drive are currently open.

The installation of the sanitary sewer line will continue down 6th Street South and connect to Bay Drive. This work is expected to be completed and restoration to begin by June 5, 2020. The installation of the sanitary sewer line on 5th Street is expected to begin by June 10, 2020. Both 6th Street and 5th Street are experiencing travel lane interruptions and closures. It would be best to avoid these roads until work is completed in August.

Force Main 8

  • Holmes Beach
The construction work on Force Main 8 in Holmes Beach is complete except for minor restoration activities. Currently, construction crews are scheduled to complete filling the existing force main pipe with concrete grout, followed by restoration of the roadway. This work is pending and will be done in coordination with the mobilization of current active projects.

Force Main 15

  • Anna Maria
The construction work on Force Main 15 in Anna Maria is complete except for minor restoration activities. Currently, construction crews are scheduled to complete filling the existing force main pipe with concrete. This work will be performed concurrently with active projects in the area. There are no anticipated impacts to the traveling public or residents.

Coquina Beach Improvements

  • Coquina Beach

The construction work on the stormwater drainage and parking area at Coquina Beach has been completed in the southern parking lot, which is part of Phase 1 of this two-phased project.

The County is working with Amerson Landscape, Inc. to install irrigation and 103 native trees in the area near the southern parking lot. This work is expected to begin next week. Construction crews have completed work on the Phase 1 stormwater drainage and parking areas. The contractor is working to complete the minor punch list items necessary to complete the contract.

Holmes Boulevard Force Main Replacement

  • Holmes Beach

The Holmes Blvd. Force Main Replacement project will replace just under one mile of 12 and 10-inch force main pipeline on Holmes Blvd from 68th Street to 52nd Street. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020

 

AMI Water Main Improvements

  • Bradenton Beach

This project will replace and upsize 2-inch and 4-inch water lines along 26th Street North, 25th Street North, and Avenue A. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020