Interactive Map

Get project specific information by clicking its name below or its location on the map.

Under Construction

In Design

Force Main 1

  • Bradenton Beach

As construction work continues along Gulf Drive on Force Main 1 in Bradenton Beach, the safety of residents, visitors, the traveling public and construction crews is our primary concern. We urge all commuters to adhere to the posted speed limit of 25 m.p.h. when traveling along Gulf Drive.

Construction crews are currently working to replace a 10-inch sanitary sewer line and a 6-inch force main pipeline along Gulf Drive between 6th Street South and 5th Street South. This work will continue down 5th Street and will connect to Bay Drive. All travel lanes on Gulf Drive are currently open however, both 6th Street and 5th Street are experiencing travel lane interruptions and temporary closures, so motorists may want to avoid 6th Street and 5th Street until the work is completed in August 2020.

During the week of May 18th, 2020 construction crews will begin asphalt replacement on Gulf Drive travel lanes and on bike paths between 5th Street South and 6th Street South. The maintenance of traffic plan will include a traffic lane shift of the northbound traffic, but there are no anticipated lane closures. The asphalt replacement, as well as the temporary striping is expected to take one day to complete. To ensure the work is completed before Memorial Day, it is tentatively scheduled for May 22nd, 2020 between the hours of 8 a.m. and 4 p.m., weather permitting.

Force Main 8

  • Holmes Beach
The construction work on Force Main 8 in Holmes Beach is complete except for minor restoration activities. Currently, construction crews are scheduled to complete filling the existing force main pipe with concrete grout, followed by restoration of the roadway. This work is pending and will be done in coordination with the mobilization of current active projects.

Force Main 15

  • Anna Maria
The construction work on Force Main 15 in Anna Maria is complete except for minor restoration activities. Currently, construction crews are scheduled to complete filling the existing force main pipe with concrete. This work will be performed concurrently with active projects in the area. There are no anticipated impacts to the traveling public or residents.

Coquina Beach Improvements

  • Coquina Beach

The construction work on the stormwater drainage and parking area at Coquina Beach has been completed in the southern parking lot, which is part of Phase 1 of this two-phased project. The County is working with Amerson Landscape, Inc. to install irrigation and 103 native trees in this area. This work is expected to begin the end of May 2020. More information will become available once the design plans are complete.

Construction crews are continuing to work on Phase 1 stormwater drainage and parking areas. The frontage road providing access between the middle and southern lot is complete and the frontage road providing access from the middle to the northern lot has been poured but must set before access will be allowed.

Holmes Boulevard Force Main Replacement

  • Holmes Beach

The Holmes Blvd. Force Main Replacement project will replace just under one mile of 12 and 10-inch force main pipeline on Holmes Blvd from 68th Street to 52nd Street. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020

 

AMI Water Main Improvements

  • Bradenton Beach

This project will replace and upsize 2-inch and 4-inch water lines along 26th Street North, 25th Street North, and Avenue A. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020