Interactive Map

Get project specific information by clicking its name below or its location on the map.

Under Construction

In Design

Force Main 1

  • Bradenton Beach

Construction along Gulf Drive has been completed and crews are continuing to clean up and restore Gulf Drive between 6th Street South and 5th Street South. All travel lanes on Gulf Drive are currently open. The installation of the gravity sanitary sewer line along 6th Street South has been completed and construction crews are currently restoring the area. In addition, the installation of the gravity sanitary sewer line on 5th Street South is currently under construction.


Upcoming work includes the continued installation of the gravity sewer line on 5th Street South. Beginning on Saturday, July 25, 2020, construction crews will work 6-days per week, Monday through Saturday, until the work is complete. This will minimize impacts to residents by expediting construction activities. In addition, the road resurfacing on 6th Street South will continue. Both 6th Street South and 5th Street South will continue to have travel lane interruptions and closures. If possible, please avoid these roads until work is completed in August 2020.

Force Main 8

  • Holmes Beach

The construction work on Force Main 8 in Holmes Beach is complete except for minor restoration activities. Currently, the work crews are scheduled to complete the filling of the existing force main pipe with concrete grout, as well as resurfacing the roadway. This work is pending and will be done in coordination with the mobilization of current active projects.

Force Main 15

  • Anna Maria

The construction work on Force Main 15 in Anna Maria is complete except for minor restoration activities. Currently, the work crews are scheduled to complete the filling of the existing force main pipe with concrete grout. This work will be performed concurrently with active projects in the area. There are no anticipated impacts to the traveling public or residents.

Coquina Beach Improvements

  • Coquina Beach

Construction crews have completed work on Phase 1 stormwater drainage and parking areas. The contractor is working to complete the minor punch list items necessary to complete the contract. Amerson Landscape, Inc. has completed the installation of 103 native trees and irrigation in the area near the southern parking lot. Phase 2 of this project has been approved by the Manatee County Board of County Commissioners. The County is currently working to procure the contract and construction is expected to begin in late summer/early fall 2020.

AMI Water Main Improvements

  • Bradenton Beach

Construction crews are currently working on the AMI Phase 32 Water Main, with improvements currently being made along Avenue A. The impacts in the area to residents and travelers are minimal.

Holmes Boulevard Force Main Replacement

  • Holmes Beach

The Holmes Blvd. Force Main Replacement project will replace just under one mile of 12 and 10-inch force main pipeline on Holmes Blvd from 68th Street to 52nd Street. This project is currently in design and is expected to start construction in 2020.

Construction scheduled to begin 2020

 

Bradenton Beach Sewer Rehabilitation

  • Bradenton Beach

The County completed the survey work for the Bradenton Beach Sewer Rehabilitation project along Gulf Drive from 6th Street to 13th Street in Bradenton Beach.