Schedule

Slide Sliver

Water Main and Force Main Installation: Below is a look-ahead schedule of upcoming project activities. Check back for updates.

Crews will be performing dewatering in the alleyways of Avenues A, B, and C, between November 20 and December 4, 2017, in preparation for installation of a 16″ force main along Avenue C.

Installation of the force main along Avenue C will commence the week of December 4, 2017 and extend through January 19, 2018. Door hangers will be distributed to Avenue C residents the week of November 6, informing them of details of the upcoming activities and providing them with other helpful information.