Below is the two-week look ahead schedule. Check back soon for the extended version.

Water Main and Force Main Installation

6th Avenue from 35th Street to Gulf Drive North:  Crews are installing water service in this area. Directional boring (drilling under the roadway) will be used in areas where the pipe crosses the road. Directional boring allows for minimal impacts to motorists and the surrounding area. These activities are anticipated to take place through the week of September 11.

Gulf Drive North (at beach parking lot) to 39th Street:  Crews will continue dewatering this segment. Dewatering is necessary prior to the installation of pipe. These activities are anticipated to take place through the week of September 18.